Toshiba 720MW Turbo-Generator Rewinds

Rewind & Upgrades

Toshiba 660MW-720MW water cooled rewind and upgrades

Bayswater and Mount Piper power stations NSW

6 week rewind durations

Generator windings reaching design end of life

  • Removal of existing windings
  • Clean conditions setup and Foreign Material Exclusion (FME)
  • New winding install – bottom bars and top bars
  • Bar seating (hose moulding) and bakeout
  • Connection brazing (oxy propane)
  • Brazing checks / SCW system leak checks
  • Wedging and lateral wedges (side ripple)
  • Anti-tracking varnish, gas baffles and monitoring systems
  • Electrical testing

All four rewinds were completed within allocated timeframe, no LTIs recorded and all tests met the acceptance criteria.

Projects

At Australian Winders, we pride ourselves on delivering innovative winding solutions that set the industry standard. Our projects span diverse industries, from mining and manufacturing to energy and utilities, showcasing our expertise in high-quality winders that drive efficiency and safety. Explore our completed and ongoing projects to see how we’re making an impact in Australia and beyond.